Microsoft Project – inputting half a day of leave

When putting in holidays for individual resources, double-click on the resource name in the Resource Sheet to open the Resource Information dialog box.

Click Change Working Time. On the Exceptions tab, type Half day (or equivalent).

Half day

From the Start dropdown, find the date of the half day holiday, then click Details.

Click Working Time, delete the second row of information, and adapt the first row to be the hours they will actually be working on that day.

Half day

Click OK twice. They will then be on a half day of work on that date.

Find out more about our Microsoft Project training in the London area or our Microsoft Project training in Wiltshire, Dorset, Somerset and Hampshire.

About jdonbavand

I am a trainer of Microsoft Office, Microsoft Project and Crystal Reports. I have called my blog "If Only I'd Known That...." because I hear it so many times in training sessions. In fact, if only I had a £100 for every time someone says "If only I'd known that." ....
This entry was posted in Microsoft Project, Microsoft Project 2010, Microsoft Project 2013, Microsoft Project 2016 and tagged , . Bookmark the permalink.

Leave a Reply

Fill in your details below or click an icon to log in:

WordPress.com Logo

You are commenting using your WordPress.com account. Log Out /  Change )

Twitter picture

You are commenting using your Twitter account. Log Out /  Change )

Facebook photo

You are commenting using your Facebook account. Log Out /  Change )

Connecting to %s