Microsoft Project – Displaying a comment on a split task on the Gantt Chart

When training Microsoft Project earlier this week, I was asked whether it was feasible to display a comment on the Gantt Chart by split tasks, to explain why the split had occurred. One approach would be to use a text … Continue reading

Posted in Microsoft Project, Microsoft Project 2010, Microsoft Project 2013 | Tagged , | Leave a comment