Microsoft Project – moving completed parts of tasks back to Status date

Sometimes on a project, some tasks actually get started ahead of schedule! In that case when we are tracking, we may want to move the bits that are done back to the Status date, so that subsequent tasks can get … Continue reading

Posted in Microsoft Project, Microsoft Project 2010, Microsoft Project 2013, Microsoft Project 2016 | Tagged , | Leave a comment

Microsoft Project – show status date

The Status date is the date at which you have the most up-to-date information for tracking on a project plan. By default it is the current date but may be an earlier date if you have received updates from the … Continue reading